Skagit County’s Capital projects typically experience several phases of design before the project is approved for construction:
- 30% (Geometric Layout)
- 60% (General Plan Set)
- 90% (Complete Plans, Specifications, & Estimate of Construction Cost (PS&E))
- 100% (Ad-Ready PS&E)
Internal review of the design is performed after each stage has been completed.
The PS&E Contract Documents are then signed by the County Engineer and routed to the Board of County Commissioners for approval to advertise for competitive bidding.